Monday Morning Round Up 4/27/26

Here’s info from dozens of listserves and notifications that aren’t clogging up your inboxes! 

John Nolen Drive Construction Update

Latest Update 4/24/2026

General Project Information

The John Nolen Drive project includes reconstructing John Nolen Drive and six bridges that span the causeway. New curb and gutter with a raised median separating northbound and southbound traffic will narrow traffic lanes to calm high traffic speeds. The Capital City Trail will be moved further from the roadway with the addition of three new bridge structures, increasing pedestrian safety and greenspace along the corridor. The trail will also be widened, increasing the capacity of the trail, with separate paths for bikes and foot traffic.

Project Schedule
  • Stage 2 Start Date: November 24, 2025
  • Anticipated Stage 2 Completion: August 2026
Current Stage / Traffic Impacts

Stage 2

Work entails reconstructing southbound John Nolen Drive, reconstructing three bridges on the causeway, and the Basset to Bedford pedestrian path.

John Nolen Dr restricted to one lane each direction on existing northbound lanes

S Broom St intersection – Phase 2

Phase 2 work entails reconstructing the S Broom St intersection between northbound John Nolen Dr and the WSOR tracks

  • Broom St (full closure) closed between W Wilson St John Nolen Dr
  • Bike and pedestrian traffic detoured to North Shore during railroad reconstruction. Railroad work performed by others under contract with WSOR.
  • A temporary “all way stop” will remain at the S Bedford St/North Shore Dr intersection to address an anticipated increase of vehicle traffic
Upcoming Work/ Traffic Impacts

North Shore Dr intersection – Phase 2

Phase 2 work entails reconstructing outbound/eastbound lanes of North Shore. Work will occur after S Broom St reopens to traffic. Anticipated start is early-June

  • North Shore Dr (full closure) closed between S Bedford St and John Nolen Dr
  • Bike and pedestrian traffic detoured to S Broom St during railroad reconstruction. Railroad work performed by others under contract with WSOR.
Work Week of 4/27/26 
  • North bridge
    • Set girders (span 1)
    • Begin framing deck
  • Middle bridge
    • Set girders (span 1)
    • Pile driving north abutment
  • South bridge
    • Curing time for bridge deck
  • Box culvert/storm sewer in Broom St
Work Week of 5/4/26 
  • North bridge
    • Continue framing deck
    • Rebar for bridge deck
  • Middle bridge
    • Pile driving north abutment
    • Framing north abutment
  • South bridge
    • Curing time for bridge deck
  • Storm sewer and earthwork in Broom St
Motorist Impacts
  • All vehicles on John Nolen Dr use existing northbound lanes between Lakeside St and the Monona Terrace.
    • Both directions of traffic are reduced to one lane prior to entering the active work zone.
    • Signs have been installed on both end of the project to provide direction on where to “zipper merge”. Motorists should utilize all lanes and avoid early merging.
  • A temporary “ALL WAY STOP” condition has been installed at the intersection of S Bedford St and North Shore Dr. This will remain in place until all work in the Broom St intersection is complete.
Pedestrian/Bike Impacts
  • The temporary crosswalk on the north side of Broom St is in place and will be the only crossing at Broom St until the project is complete. Sidewalk along the southern side of Broom St is open between W Wilson St and the Brittingham Dog Park.
  • The Capital City Trail remains open. No additional trail disruptions are anticipated until July of 2026. Cyclists are encouraged to dismount from their bikes when crossing active construction zones near S Broom St and North Shore Dr.
Waterway Impacts
  • A navigable channel will be open for the duration of the project under the middle set of bridges. The channel has red and green buoys to aid navigation and regulatory buoys to delineate hazards. No other channels will be open and waterway users should avoid entering areas with active construction
  • Please be alert when traveling along the John Nolen Drive corridor. Please note that some work is dependent on weather and may be subject to change. Thank you in advance for your patience throughout this project.
Progress Photos
John Nolen Drive Construction
John Nolen Drive Construction
John Nolen Drive Construction
John Nolen Drive Construction
John Nolen Drive Construction
John Nolen Drive Construction

 

PROJECT UPDATES

CCB Capital Needs Assessment

Location: 210 Martin Luther King Jr Blvd
Estimated Schedule: March 2, 2026 – September 30, 2026

Project Overview

The City of Madison is beginning a Capital Needs Assessment of the City County Building to better understand the facility’s long‑term maintenance and repair needs. This review will look at the building’s major systems – such as structural, mechanical, electrical, and plumbing to document their current condition and identify any issues that may require attention. The assessment will also estimate future maintenance and improvement costs. The results will help guide Operating and Capital budget planning to keep the building safe, functional, and reliable for the community.

Project Schedule

City User Agency: City of Madison Engineering

A/E Consultant RFP Advertisement: July 17, 2026
A/E Consultant RFP Due Date: August 22, 2026
RFP documents will be found on VendorNet and DemandStar when published
“All information regarding dates/times/locations are informational and should be verified with the RFP documents”

Assessment: March 2026 through September 2026

View project information

South Franklin Ave., Ridge Road, Sylvan Ave. Reconstruction

Location: 138 S. Franklin Ave
Estimated Schedule: April 5, 2027 – November 19, 2029

April 24, 2026 Update

This page has been created. The City will begin with the public engagement in the summer of 2026 and preliminary design in the fall of 2026.

View project information

Imagination Center at Reindahl Park

Location: 1818 Portage Road
Estimated Schedule: April 28, 2025 – July 31, 2026

April 22, 2026 Update

April 2026 Update
Construction progress across the project site continues at a steady pace as interior finishes, building systems, and early site work move forward in coordination. Over the past month, crews reached several interior milestones, including the completion of Phase 1 and Phase 2 storefront systems, drywall finishing, and prime-and-paint activities. Casework delivery and installation have also been completed, adding functional elements to rooms and work areas. Bathroom tile installation and continued above‑ceiling rough‑ins have further advanced readiness for inspections and mechanical, electrical, and plumbing (MEP) finish stages.

Interior progress has transitioned smoothly into the next phase of work. Crews have begun installing the ceiling grid, which will support lighting, diffusers, and other overhead components. MEP ceiling rough‑ins and above‑ceiling inspections are underway, helping ensure systems are properly coordinated before ceilings are closed. Installation of wall protection, lockers, and bathroom accessories has also started, bringing durable and operational features into corridors, restrooms, and program spaces. In addition, site work has begun.

Looking ahead, site work will continue to expand as weather conditions allow, supporting grading, utilities, and exterior circulation improvements. These efforts will run in parallel with ongoing interior finish activities, material deliveries, and inspections. Coordination among contractors, inspectors, and project management teams remains active to maintain progress and keep the project moving toward its next major milestones as spring construction accelerates.

Visit the project’s Flickr album to view progress photos during construction along with the live construction site camera.

City Process Meetings
April 21, 2026 Common Council File #92545
April 08, 2026 Board of Public Works File #92545
Awarding Public Works Contract No. 9757, Imagination Center Fiber Connection

View project information

Meyer Avenue Reconstruction

Location: 3920 Meyer Avenue
Estimated Schedule: March 16, 2026 – July 3, 2026

April 21, 2026 Update

The first spring yard waste / leaf collection for residents on Meyer Avenue between Glenway St & Holly Avenue will be delayed due to the construction project.  Residents within the project area should place their yard waste into bags (preferably brown paper bags). Street crews will be through these blocks first thing in the morning of Monday, May 4 for their first pickup of the spring. Residents will also need to have their yard waste in bags for their second yard waste pickup. The second pickup will occur as scheduled the week of May 10.

The Contractor has completed installation of underground storm and sanitary sewer utilities for the project.  They are now excavating and installing new base course (starting at Holly Ave and working east towards Glenway St) and grading the street, which will take approximately 2 weeks to complete.  After finish grading is complete, the contractor will begin installation of concrete curb & gutter, driveway aprons, and sidewalk curb ramps, followed by restoration of the terrace and installation of terrace rain gardens.  The Contractor is still on schedule despite recent storms and the project is expected to be completed by July 3, 2026.

View project information

Bartillon Shelter

Location: 1904 Bartillon Dr
Estimated Schedule: May 2, 2022 – January 30, 2026

April 21, 2026 Update

Surplus brick, pavers and glazed CMU from this project are currently being auctioned as Lot #87364 on Wisconsin Surplus Online Auction #26-548 – Multi-Muni – Multi-Location Auction – Wisconsin.  The auction ends on May 05, 2026 @ 10:20 a.m.

View project information

Project Update: Sauk Creek Greenway

Location: 7425 Farmington Way
Estimated Schedule: June 1, 2020 – December 31, 2025

April 21, 2026 Update

Today City of Madison Engineering staff will be conducting a prescribed burn on two small pollinator plantings along the western edge of Sauk Creek Greenway along the border with Haen Family Park.  Prescribed burns are an important management tool for Wisconsin’s native plant communities. Please read more about the use of prescribed burns for vegetation maintenance on stormwater land on our website: https://www.cityofmadison.com/engineering/stormwater/programs-initiatives/prescribed-burns

Or in the Stormwater Utility Vegetation Management Plan: https://www.cityofmadison.com/engineering/documents/projects/Final%20SWUVegetationPlan.pdf

The City mailed postcards to residents within 400′ of the planned burn site to notify them about the prescribed burn in their area. All burns are being conducted by certified burn professionals with approval by Madison Fire Department. The burn only takes place under specific weather conditions in order to manage smoke and minimize impacts to neighbors. In addition, the burn professionals will install appropriate road signage.

View project information

Project Update: West Towne Pond Improvements

Location: 6705 Mineral Point Road

April 20, 2026 Update

View project information

Hawthorne Court Road Reconstruction

Location: 425 Hawthorne Court
Estimated Schedule: May 2, 2026 – August 14, 2026

April 20, 2026 Update

The Contractor has completed installation of the water services and sanitary sewer main and laterals on Hawthorne Ct.  They are completing the installation of storm sewer, testing of sanitary sewer, and connecting electrical services this week.  Following completion of the underground utilities, the contractor will finish grading the street and then install concrete pavement and sidewalk.  The Contractor is anticipating their work on Hawthorne Ct to be finished ahead of schedule, the week of May 15.

After work on Hawthorne Ct is completed, the Contractor will begin work on N. Lake St installing a small section of sanitary sewer main, resurfacing the street, and placing new pavement markings.  The work on N. Lake is anticipated to take approximately 3-4 weeks to complete.

Allowed working hours are 7:00 am to 7:00 pm Monday – Saturday and 10:00 am to 7:00 pm Sundays.

During construction, Hawthorne Ct will be closed to through traffic.  No street parking is allowed on Hawthorne Ct. The Parking Division will supply residents with free parking permits for one month during construction. Requests for permits can be made by calling the Parking Division at 608-266-4761 or emailing monthlyparking@cityofmadison.com.  The Contractor will notify impacted residents prior to their driveway access being closed for an extended period of time (e.g. underground utility work, concrete drive apron curing, etc.)

View project information

Buffalo Trail, Barron Court, Green Lake Pass

Location: 5117 Buffalo Trail
Estimated Schedule: April 6, 2026 – June 26, 2026

April 15, 2026 Update

Construction is underway on Buffalo Trail, Barron Court, and Green Lake Pass. The Contractor has completed installation of the mainline sanitary sewer and has two laterals remaining before transitioning to storm sewer work the week of April 21. Work is finishing to complete soil removal and place the lower layer of gravel on Green Lake Pass.

The Contractor will begin installing storm sewer along Buffalo Trail, which is expected to take approximately three weeks. Following storm sewer installation, crews will remove unsuitable soils and place the lower layer of gravel on Buffalo Trail. Once all lower gravel is in place, the roadway will be prepared for curb and gutter installation.

During curb and gutter placement, driveway access will be limited because the concrete has to dry. Construction staff will notify property owners in advance. Curb and gutter installation is currently planned for mid-May.

Jim Gottschalk, 608-261-9115,  jgottschalk@cityofmadison.com, will be the best on-site contact throughout construction.

View project information

Free Fair Housing Training – Madison

Hello,

I hope you had a wonderful week! I am writing to remind you that the Fair Housing Center of Greater Madison is offering a free in-person fair housing training seminar for owners and managers of rental properties, or staff operating shelters or residential programs, in Madison. Please note that this training is intended for housing providers, not housing consumers or members of the general public. If you are interested in scheduling a fair housing presentation for consumers, a service provider, or any other community-based group, please contact us at 414-278-1240.

Thursday, May 21, 2026
2:00 p.m. – 4:30 p.m.

Madison Public Library, Goodman South Branch

2222 S. Park Street, Meeting Room 115

To register for this seminar, visit https://tinyurl.com/MadisonFHTrainingMay2026or call 414-278-1240.

The seminar will include information about the protected classes and prohibited practices delineated by local, state, and federal fair housing laws, as well as reasonable accommodations and modifications for tenants with disabilities.

Please share this information and the attached flyer widely.

DEMOLITION NOTICE

This is a notice that Vincent Bixby will be filing a demolition permit application. The application will be submitted around April 25, 2026 or later. The applicant seeks to demolish a Commercial Building. The address is 1440 Monroe St Madison, WI 53711.

The City’s Landmarks Commission provides an advisory review of all demolition applications. The Landmarks Commission will determine if the building has historic value. If it has historic value, then the Plan Commission will review the application. The Plan Commission will hold a public hearing when they review the application. If it has no known historic value, the Director of Building Inspection may approve the application.

For more information about this application, please contact the applicant, Vincent Bixby, Omega !!!, LLC, 31W566 Spaulding Road Elgin, IL 60120 at vinnyb@omega3llc.com or (630)837-3000.

Applicant’s Comments:

Demolition of the McClain Center Fieldhouse Building for the University of Wisconsin at Madison.

If you have any questions about the City’s application review process, please contact the City of Madison Planning Division at (608) 266-4635.

Affordable Rental Development: Non-Tax Credit Request for Proposals (RFP)

The City of Madison Community Development Division (CDD) has released the Affordable Rental Housing Development: Non-Tax Credit Request for Proposals (RFP). This RFP focuses on capital support for non-tax credit rental housing development within the City of Madison. This RFP will allocate up to $6 million in Federal and City funds to support the goals and strategies to create affordable housing opportunities.

The CDD will hold an RFP Application Workshop designed for developers interested in applying for City financial assistance in response to this RFP. Staff will provide an overview of the RFP, the Affordable Housing Targeted Area Map, and key requirements and preferences.

Registration is required to attend.

Please register for the RFP Application Workshop by May 4th. The virtual application workshop will be held on May 5th at 11 AM.

Please direct all questions on this Request for Proposals to John Vogt, Community Development Specialist, at jvogt@cityofmadison.com.

Thank you,

John Vogt | Community Development Specialist
Department of Planning and Community & Economic Development
Community Development Division

Madison Municipal Building | Suite 300
215 Martin Luther King, Jr. Boulevard | Madison, Wisconsin  53703-3348

Mail  P.O. Box 2627 | Madison, Wisconsin  53701-2627
Tel  608 267 0742 | Fax  608 261 9661
Email jvogt@cityofmadison.com
Web cityofmadison.com/cdd

May Messenger

The May Messenger is now available on the website. May is Older Americans Month. Let’s celebrate how all people make valuable contributions to our country regardless of their age!

Metro Rider Alert

April 23, 2026

Potential Service Disruptions

Metro may experience service disruptions on select trips this afternoon. Please check our Bus Availability page for updates.

We encourage riders to use the Bus Tracker to check your trip. Sign up to receive text messages for service alerts.

Full Details

Upcoming Detours!

 Route C – Saturday, 4/25 until 2:05p
Buses detour from a portion of University Ave.

 Route D – Saturday, 4/25 until 2:05p
Buses detour from a portion of Monroe St.

 Route 80 – Saturday, 4/25 until 2:05p
Langdon, Charter, Linden and Observatory are closed.

 Route C (eastbound) – Saturday, 4/25 ALL DAY
Buses detour from Bassett and Wilson streets.

 Route 81 – Saturday, 4/25 ALL DAY
Portions of Gorham, Lake, Dayton and Bassett are closed.

Main Detour Page

May Service Updates

In Effect: Sunday, May 10
Upcoming Changes:

Routes H & O
Will board across the street from the existing stop at the new (westbound) bus stop location on Hughes. Please review the map below for reference.

Route G
Will board across the street from the existing stop at the new (eastbound) bus stop location on Hughes. Please review the map below for reference.

Schedule Updates:

  • Route C – Timepoint/Schedule Adjustments
  • Route D – Timepoint/Schedule Adjustments
  • Route G – Route Change on Hughes & Park
  • Route H – Route Change on Hughes & Park
  • Route O – Route Change on Hughes & Park
  • Route S – Timepoint/Schedule Adjustments
  • Route 38 – Timepoint/Schedule Adjustments

New Bus Stops

New stops opening on University Avenue at Blackhawk serving Routes R, 28 & 38.

New Bus Stop IDs: 

  • Westbound: 2266
  • Eastbound: 2757
Complete Details

 

 

DANE COUNTY REGIONAL HOUSING NEWS

Regional Housing News – April 2026

Facebook  Instagram  Web  Email

IN THE NEWS

RHS Housing Spotlight:

Community Land Trust Housing – New Fact Sheet Available

2026 Annual Regional Housing Strategy Meeting – SAVE THE DATE!

Tuesday, June 30, 2026, 6:00PM

NEW WI Legislation to Address the Housing Shortage

May is Affordable Housing Month!

Community Updates…Calling All Realtors!

Upcoming Events & In the News…

Regional Housing Strategy Spotlight:

Community Land Trust Housing

The RHS Action Plan identifies expanding community land trusts (CLTs) as a strategy to increase the number of affordable homes for Dane County residents.

CLTs are nonprofit organization that provide affordable single-family housing to low- to moderate-income individuals and families. CLTs offer housing at below-market rates and can provide single-family housing through new development or through acquisition and rehabilitation of older housing stock.

When you buy a single-family home, the ownership includes the house and the land underneath it. When you buy a home from a CLT, you purchase the house but lease the land for a small fee. Because the cost of the home does not include the cost of the land, the home price is significantly reduced compared to market rate single-family housing.

Municipalities can partner with community land trusts in a variety of ways to bring affordable single-family housing to their residents. Interested in learning more about CLTs and how they work? For information about how to bring CLTs to your community, or to hear a presentation on land trust housing, reach out to Mason Cavell, MACLT Executive Director, at mason@maclt.org.

Community Land Trust Housing

FACT SHEET NOW AVAILABLE—

The Regional Housing Strategy’s newest fact sheetCommunity Land Trust Housing, is now available on the RHS Website. This fact sheet gives an overview of community land trusts (CLTs) and their role in providing permanently-affordable housing in the community, and includes some first steps for municipalities who are interested in bringing a CLT into their community.

Additional Resources— Learn About CLTs

Community Land Trusts: A Guide for Local Governments – National League of Cities

Read more about community land trusts, and the steps that municipalities can take to start and sustain a community land trust in their community.

Startup CLT Hub – Grounded Solutions Network

Want to bring a CLT to your community, but are unsure of where to start? Check out this CLT startup tool kit from Grounded Solutions Network, including questions to consider when trying to bring CLT projects into your community, and suggested steps to take to develop a CLT organization.

Local and National Examples of CLTs

Community Land Trust Builds Black Generational Wealth in Pricey Orlando Suburb – American Planning Association

Read about the Hannibal Square Community Land Trust, a Florida CLT that was started to prevent the displacement of Winter Park, Florida’s African American residents, and since expanded its mission into creating affordable housing throughout Central Florida.

____

Habitat for Humanity and Missoula Land Trust Team up on Affordable Housing – Planetizen

Learn about Habitat for Humanity’s partnership with the North Missoula Community Development Corporation Land Trust (now known as the Front Step Community Land Trust), and how they are working to create a variety of affordable housing types in Missoula, Montana.

 

____

How One Community Land Trust Delivers Housing Affordability to Denver– Planetizen

Elevation Community Land Trust in Denver, Colorado is a CLT with hopes of creating 1,000 affordable homeownership opportunities for Denver families from 2017-2027. Read more about the Elevation CLT and how they are funding their 1,000 home goal.

____

Madison Adds 2 New Affordable Homes to Mosaic Ridge Neighborhood– Spectrum News

Dane County’s local CLT, Madison Area Community Land Trust, in a partnership with the City of Madison created two new permanently-affordable homes to Madison.

Please share the RHS newsletter and invite your friends to sign up here!

SAVE THE DATE
2nd Annual

Regional Housing Strategy (RHS) Meeting

Tuesday, June 30, 2026

6:00-8:30 PM

Alliant Energy Center

At the meeting, you will learn about regional progress on the RHS’s Five Housing Priorities! You’ll hear from a panel of elected officials about the challenges and tough decisions they face around addressing the housing crisis and opportunities to improve outcomes.

We’ll also discuss the obstacles to building and preserving affordable single-family housing, What do affordable single-family homes look like, and how do we make it happen? Ice cream will be served! Free and open to the public – all welcome! Stay tuned for updates. Mark your calendars!

Wisconsin Legislature Provides New Help

to Address Housing Shortage, Affordability

The Wisconsin legislature has passed numerous bipartisan bills that provide municipalities with expanded tools to increase housing supply and address the affordability crisis.

WI Act 194— Modifies WHEDA Housing Loan Programs

Wisconsin State Legislature updated the Wisconsin Housing and Economic Development Authority’s (WHEDA) new workforce housing loan programs: Infrastructure Access, Restore Main St., and Vacancy and Vitality, to expand utilization of the fund and increase housing supply. Highlights include:

 

  • Allowing tax incremental financing and historic tax credits to be stacked with housing loans to ensure that all financing gaps and cost constraints may be addressed
  • Increasing the maximum loan amounts that may be awarded in all three programs measured either as a percentage of project cost or a per unit dollar figure
  • Lowering the number of dwelling units that must be created in the Vacancy-to-Vitality Program for municipalities under 10,000 in population from 16 or more to 4 or more
  • Allowing mixed-use developments to qualify for the Vacancy-to-Vitality Program while ensuring loan funds are only used for the residential portion of the development
  • Moving the lookback date from January 1, 2023 to January 1, 2020 for municipal ordinance or other regulatory changes necessary for the cost reduction analysis.

____

WI Act 234— Creates a Workforce Housing Tax Incremental District (WF-TID)

Starting October 1, 2026, the legislation creates a new Workforce Housing tax incremental district (TID), which incentivizes new single-family or duplex residential development. Under this legislation, a Workforce Housing TID can be created if the following conditions are met:

  • The total value of all Workforce Housing TIDs do not exceed 3% of total equalized value of the municipality, (WH-TID exempt from the 12% cap for communities); the TID lifespan does not exceed 20 years, and the costs are limited to supporting the necessary infrastructure and certain related expenses
  • The development is for owner-occupied single-family or duplex residences that are 1,500 square feet or less for single story residences or 2,000 square feet or less for two-story residences
  • The lot sizes and widths are not greater than 7,500 square feet and 70 feet for single-family or 12,500 square feet and 80 feet for duplexes and, for either, side setbacks are not greater than 10 feet.

____

WI Act 173 — Changes to Residential Rezoning Requirements

On April 8, Governor Tony Evers. signed the “Truth in Planning” Bill, that requires cities’ and villages’ zoning ordinances to be consistent with their comprehensive plans, particularly in identifying areas where houses and specific densities will be allowed.

Under this legislation, municipalities must grant rezoning requests for residential development if the proposed area is designated for residential use in the municipalities’ comprehensive plan, aligns with existing development, meets certain density requirements, and addresses housing demand in their community. Municipalities must now identify exactly where and how densely residential growth will occur in five-year increments.

_____

WI Act 175 – Expands TIF Extension to Three Years for Affordable Housing

This legislation modifies tax incremental financing provisions, allowing municipalities to extend a TID upon closure from one to three years, and expands what can be included as project costs within the TID. 75% of the funds must be used for affordable housing, the other 25% for other housing stock.

This new legislation will take some time to implement and get underway, but reflects important new tools and next steps to address the housing shortage and affordability crisis.

May is Affordable Housing Month

As part of Affordable Housing Month, Dane County municipalities and organizations are spreading awareness about the need for more affordable homes and housing units in our community. Check out some of the educational events next month and please join in! Free and open to the public!

Sun Prairie Affordable Housing Month

The City of Sun Prairie is partnering with community organizations to offer a variety of events aimed at increasing understanding and involvement in housing. To learn more about Sun Prairie’s affordable housing events, visit their housing website here, and check out one of their featured events below!

Small Homes, Big Impacts: A Talk on ADUs

Thursday, May 7, 2026, 7:00-8:00PM

2598 W. Main Street (Sun Prairie)

Many communities are seeking ways to add housing that fits its neighborhoods. Join us to discuss Sun Prairie’s draft accessory dwelling unit (ADU) ordinance, hear from a developer building these units, and listen to a homeowner that recently completed one in Madison.

____

Madison Housing Week

Madison Housing Week brings together residents, policymakers, advocates, and experts to learn about how housing and land use decisions that impact everyone. This week-long event features webinars, panels, and neighborhood tours that explore topics such as housing affordability, zoning and land use, community engagement, accessory dwelling units, and much more. To see the events planned for Madison Housing Week, visit the event website here, and check out one of the featured webinars below!

 

Lunch and Learn: Madison Housing Market Update

Monday, May 4, 2026, 12:00-1:00 PM

Join AARP for a free webinar about what is happening in Madison and Dane County’s housing markets. You will hear from community experts in home building, real estate, and planning, as they discuss what is driving change in Madison and Dane County, and what it means for local homeowners and homebuyers.

To register for this event, click here.

Visit the Regional Housing Strategy Website Here

Calling All Realtors!— Fair Housing Challenge

The Wisconsin Realtors Association has launched their Fair Housing Challenge, inviting realtors to build a more inclusive, equitable, and educated real estate profession. Through the completion of three programs, realtors can learn more about the history of fair housing, as well as the ongoing challenges surrounding fair housing.

To learn more about the challenge, or the programs offered in this course and get involved, visit the Wisconsin Realtors Association website here.

Community Housing Highlights

City of Middleton Housing Action Plan, New Release

The City of Middleton’s Community Development Authority and Workforce Housing Committee developed its Housing Action Plan: Addressing Affordability in Middleton, Wisconsin (2026-2036), outlining how Middleton’s Affordable Housing Fund will be used over the next decade. The plan sets key strategies and actions to guide efficient use of the funds.

 

The Housing Action Plan presents an ambitious yet practical vision, informed by best practices and aligned with the Dane County Regional Housing Strategy, with the goal of making the fund a long-term resource for housing affordability in Middleton.

____

City of Fitchburg, New Housing Study and Action Plan

The City of Fitchburg has adopted their 2026 Comprehensive Housing Study and Action Plan, which addresses Fitchburg’s current and future housing needs while supporting sustainable growth. The Housing Plan was developed with input from residents, advisory committees, city staff, and community stakeholders, and will serve as a guide for city policies and future decision-making. To view the City of Fitchburg’s housing study, click here.

____

$241,000 Awarded to Local Housing Developer

FHLBank Chicago awarded $241,000 to Madison-based firm, Kaba-Baal LLC, through its Community First Developer Program. This funding will be used to create additional pathways into affordable housing development for aspiring professionals across the state.

Kaba-Baal LLC, founded by developer Kaba Bah, works on creating homeownership opportunities that strengthen neighborhood stability. The Developer Program grant awarded to Bah’s firm will support fellowships and internships for many future professionals who will learn more about property management, planning, and community engagement, while also understanding how development can be used to expand opportunities for families.

Upcoming Events

Collaborating to Strengthen Dane County Through Housing

Thursday, April 23, 2026, 8:00-11:00 AM

Anderson United Way Center (2059 Atwood Avenue, Madison)

Dane County Housing Access and Affordability and United Way invite you to join them for a conversation about increasing access to housing in Dane County. Join us for a discussion about the housing landscape in Dane County and learn about two affordable housing funds. Additionally, you will have the chance to learn more about Greenlight, and provide feedback to its developers about what this tool could look like in your community!

To register for the event, click here.

____

Join Habitat for Humanity— Community Discussion on Tackling the Affordability Crisis

Wednesday, April 22, 2026, 8:00 AM

Join Habitat for Humanity for Turning the Key to Homeownership, a community discussion that is free to the public!

Jim Malewitz, WI Watch, will facilitate a solutions-focused event uniting business and government leaders, nonprofit partners and community champions working to expand access to affordable housing.

Breakfast and networking begins at 8:00 am.

Register here

____

FREE Homebuyer Education Course

May 5, 12, and 19, 2026, 5:30-8:30 PM

The Hub, 4th Floor (2352 S. Park St., Madison)

Dreaming of owning a home but not sure where to start? Join the Urban League of Greater Madison’s Free Homebuyer Education Course, designed to make the homebuying process achievable. In this course, you will learn to improve your finances, navigate the homebuying process, and qualify for grants and assistance programs such as downpayment assistance, lower interest rates, and special programs for buyers with lower credit.

To RSVP for this event, click here.

____

Home Efficiency and Electrification Mini Course

May 5, June 2, June 30, & September 22, 2026, 5:30-7:30 PM

StartingBlock Madison (821 E. Washington Avenue, Madison)

Are you interested in making your home more energy efficient? Join Sustain Dane and MG&E’s Home Efficiency & Electrification Course, a mini course that will help homeowners understand their home’s energy use, explore options to reduce your home’s carbon footprint, and plan next steps!

This series of courses takes place over four Tuesdays (May 5, June 2, June 30, and September 22) from 5:30-7:30PM. Dinner will be provided. The cost of this series is $60, with sliding scale scholarships available. Questions about this course can be directed to samantha@sustaindane.org.

____

FREE Training Seminar

Fair Housing: Do You Know the Law?

Thursday, May 21, 2026, 2:00-4:30PM

Madison Public Library, Goodman South Branch (2222 S. Park Street, Meeting Room 115, Madison)

Are you an owner or manager of Madison rental housing who is interested in learning more about Fair Housing Laws? If so, you are invited to attend the Fair Housing Center of Greater Madison’s free training seminar on Fair Housing on Thursday, May 21, 2026, 2:00-4:30 PM. At this seminar, you will learn about local, state, and federal fair housing laws, as well as topics such as:

  • Advertising units in compliance with fair housing law
  • Non-discriminatory negotiation with prospective tenants
  • Interacting with current tenants in a fair and legal manner
  • Reasonable accommodations and modifications for tenants with disabilities.

To register for this training, click here or call (414) 278-1240.

In the News…

April 08, 2026, Channel 3000— Homeownership is slipping out of reach in Dane County

April 03, 2026, Leader Independent— Harvest Corners: Developer breaks ground on new McFarland housing project

March 27, 2026, Wisconsin Public Radio— ‘You can’t erase history’: Dane County is mapping racist language in housing deeds

Questions? Send an email to regionalhousing@danecounty.gov for questions or more info on the Dane County Regional Housing Strategy.

 

PARKS UPDATES

Madison Parks logo, over a blue sky with white clouds.

Seasonal Restrooms

Most seasonal restrooms that closed for the winter will reopen on Saturday, April 25. See Restrooms for open locations.

New Disc Golf Baskets Coming to Madison’s Courses

Madison Parks is excited for the new disc golf baskets for both Elver and Hiestand: Innova Tour Targets (red – short and blue – long). It’s been a journey getting the 70+ baskets assembled and ready for install and play. We appreciate your patience and look for opening updates soon on the Disc Golf page.

Seeking Public Input: Reimagining Odana Hills

The City of Madison Parks Division is excited for the new partnership with Michael and Jocelyn Keiser and the Madison Parks Foundation. Through the Keisers’ philanthropic vision and generous donation, we have an opportunity to reimagine, redesign and reconstruct Odana Hills Golf Course. The baseline course improvements will address tee boxes, green complexes and surrounds, along with some potential for routing adjustments.

In addition to the golf course improvement project, the City is planning to leverage the private donation and take advantage of the temporary closure of the property in a way that allows for public infrastructure improvements to both Odana Hills Golf Course and Odana Hills East Park.

The Learning Series

The Learning Series features educational events, hands-on workshops, and informational stories about projects, people, activities, and initiatives. The Learning Series is free to all, thanks to the Madison Parks Foundation.

  • Learn to Play Ultimate – Saturday, May 16
  • Gratitude in Nature: Habitat Restoration, Animal Encounters & Yoga – Sunday, June 7
  • Learn to Fish – Wednesday, June 10
  • Learn to Kayak – multiple dates & locations
  • Learn to Standup Paddleboard Yoga – Tuesday, June 30
  • Learn to Drive a Pontoon – Tuesday, July 7
  • Learn to Canoe – Wednesday, July 15

Advanced registration is required and may be done online or by calling. See Learning Series for more information.

Ride the Drive 2026

With RTD’s signature route along John Nolen Drive under construction, we have an exciting redesigned new route for 2026!  Join us on Sunday, August 9 from 10:00am to 2:00pm to stroll, roll, pedal or glide your way along the roughly 3-mile loop that includes activity hub stops at:

  • McPike Park, 202 S. Ingersoll
  • Lakefront Porch Park, 201 S. Hancock
  • Capitol Square, Mifflin & Carroll

See RideTheDrive.com to check out the route map, be a vendor/exhibitor (free for most organizations!), or register to be a volunteer.

Leave No Trace

With the warmer temps and sunshine, we love seeing people out and about and the steady increase of park visitors throughout the city. To help keep your parks clean and inviting to everyone, before you depart, remember to take all your belongings and leave no trace – this includes toys and other personal items. While it may seem thoughtful to leave toys behind for others, these items can quickly become safety hazards and can be considered abandoned property that may be removed. See MGO 8.44 – Lost or Abandoned Property for more information.

Bus Parking Reminder

Madison Parks offers free bus parking in the rear lot of Duane F. Bowman Park, 1775 Fish Hatchery Rd. This is ideal for school field trips, conventions and tour groups. To best allow park users access, all other locations, including Olin Park, Turville Point Conservation Park or along Vilas Park Dr. are prohibited and subject to a citation. See Bowman Park for location and download, save and print the parking map.

Breese Stevens Gets New Artificial Turf

The installation of new artificial replacement turf is complete at Breese Stevens Field and just in time for its 100-year anniversary. The previous artificial turf system, installed in 2014, reached the end of its useful life, and its replacement was a necessary part of facility maintenance to ensure the continued use of the field for athletic events. See Breese to learn more about this project.

Updates

  • Olin Park Pedestrian Bridge – the new pedestrian bridge over Wingra Creek is expected to be installed on May 4, weather permitting. In preparation and during the installation, several parking stalls will be closed at the boat launch in the construction zone area. See Olin Pedestrian Bridge for more information.
  • Playground replacements – demos underway, followed by installation of a new playground – Kennedy, Sandburg, Ontario, and Skyview. Playgrounds and the surrounding areas will be closed during construction which is expected to be completed by August 14 for all four parks. See Projects for more information.
  • Warner Park Boat Launch Restrooms – initial findings of the boat launch building found extensive settling issues causing the plumbing to break apart and fail. This project will be managed by City Engineering. The restrooms will remain closed until further notice and portable unit is onsite.
  • Warner Park Community Recreation Center expansion is nearly complete, with just a few final touches remaining. Thank you for your patience as we prepare new programs and enhanced facilities. Stay tuned for updates later this spring at WPCRC!

 

 

 

20262028 Dane County Board Term Begins

Supervisors sworn in, board officers elected 

DANE COUNTY, Wis. — On Tuesday, April 21, 2026, the Dane County Board of Supervisors officially began its 2026–2028 term during its organizational meeting.

During the meeting, all 37 supervisors were sworn in, including 5 new members joining the board. Following the swearing-in ceremony, supervisors elected board officers for the new term.

New Members of the Dane County Board:

Aria Trucios (District 9)

Goodwill Obieze (District 16)

Paula Brandmeier (District 20)

Gussie Lewis (District 22)

Donald Dantzler Jr. (District 33)

2026-2028 Dane County Board Officers:

Chair, Patrick Miles (District 34)

First Vice Chair, Yogesh Chawla (District 6)

Second Vice Chair, Richelle Andrae (District 11)

Sergeant at Arms, Henry Fries (District 5)

Sergeant at Arms, Gussie Lewis (District 22)

“Congratulations to each of you for being elected or re-elected to the county board. We have challenging work ahead,” County Board Chair Patrick Miles said in remarks to the board. “I see each county board term as a chapter in a long, unfolding story that began long before us and will continue long after. We are the stewards of the legacy of those who came before us, and I am excited to see what we, the co-authors of this next chapter, will write together.”

In the coming weeks, Chair Miles will announce supervisor appointments to the board’s seven standing committees, as well as additional county committee assignments. The next regular meeting of the Dane County Board of Supervisors is scheduled for Thursday, May 14, 2026.

The second issue of Madison’s Vision Zero Quarterly Newsletter for 2026 has arrived!

The second issue of  Madison’s Vision Zero Quarterly Newsletter for 2026 has arrived!

This issue explores the comprehensive, data-driven framework behind Madison’s urban planning and safety initiatives. It highlights how the City collects and analyzes data—including traffic reports, high-injury network (HIN) maps, and community input—to inform future projects, ensure equity, and enhance infrastructure. A key focus is the City’s commitment to the Vision Zero initiative, which uses this evidence-based approach to strategically direct resources toward eliminating fatal and serious traffic injuries.

This edition of the newsletter features the following articles:

  • Madison Crash Facts
  • Wisconsin Community Maps
  • MPO Safety Data and Applications
  • Centralized Traffic Signal Management
  • City of Madison Vehicles – Telematics Safety Data
  • City of Madison High Injury Network

The  Vision Zero website also offers additional information about:

Water Main Flushing plans beginning Monday April 27th (all flushing is daytime unless otherwise noted)

MAP:  https://www.cityofmadison.com/water/documents/water-quality/FlushingSchedule.pdf

East (Area 7) – South of Schlimgen Ave. between N Sherman Ave. and Packers Ave.

East (Area 24) – Blair St. to the Yahara River south of E Washington Ave.

South (Area 18) – Between Park St. and Todd Dr.

West (Area 12) – East of Whitney Way between Mineral Point Rd. and the Beltline

————

Questions: Shayne Santi, 261-9128

Flushing Information Line: 261-9178

DETAILS:

Area 7 (East): 5-7 runs per day

Run ID Run Description

7001    N Sherman from Schlimgen to Roth St

7002    N Sherman Ave from Roth St to Michigan Ct

7003    Commercial Ave from N Sherman Ave to Ruskin St

7004    Commercial Ave from Ruskin St to Packers Ave

7020    N Sherman and Fordem from Michigan Ct to Northfield Pl

7021    Superior St – Michigan Ct (Commercial to Sherman)

7022    Superior St – Erie Ct (Michigan to Sherman)

7023    Superior St and Northfield Pl

7024    Sherman Ave from Fordem to N Thornton Ave

7024.2 Sherman Ter #1

7024.3 Sherman Ter #2

7024.4 Sherman Ter #3

7024.5 Sherman Ter #4

7100    Pennsylvania Ave between First and Commercial (Northbound AND Southbound)

7101    Fordem Av – E Johnson St (Sherman to Second)

7102    S side Fordem connection loop (directly N of Johnson)

7103    W & N sides Fordem connection loop (directly N of Johnson)

7006    Packers Ave from Commercial to Aberg

7007    Everett St

7008    Packers – Aberg N to vacated Skuldt St

7009    Roth St

7010    Myrtle St (W end)

7005    Schlimgen Ave from Sherman Ave to Packers Ave

7012    Spohn Ave and Loftsgordon south of Spohn

7013    Boyd Ave and Crowley Ave

7014    Boyd Ave and O’Neill Ave

7015    Boyd Ave and Loftsgordon Ave

7016    Kropf Ave and Ruskin St

7017    Roth St

7018    Huxley St

7019    O’Neill Ave, Stephen St, Ruskin St

 

Area 24 (East): 5-7 runs per day

Run ID Run Description

24563  E Wilson – S Dickinson to Few

24563.2           S Few St – Williamson to Wilson

24566  S Thornton Ave – Williamson to Railroad St

24567  E Wilson St – Thornton to Dickinson

24568  S Few St – Williamson to Spaight

24568.2           S Few St – Spaight to south end

24569  S Baldwin St – Williamson to Rutledge

24570  Spaight, Dickinson, Rutledge to Thornton

24571.1           Spaight St – Few to Dickinson

24571.2           S Dickinson St – Williamson to Spaight

24572  Jenifer St – Baldwin to Thornton

24573  Spaight St – Dickinson to Thornton

24574  Rutledge St – Dickinson to Ingersoll

24576  S Baldwin between Rutledge and Morrison

24577  Morrison St – Dickinson to Baldwin

24578  Morrison St – Dickinson to Rogers

24579  Rogers, Morrison, S Thornton

24580  Rogers St – Rutledge to Jenifer

24581.2           Thornton – Rutledge to Spaight

24581.3           Thornton – Williamson to Spaight

24582  Rogers St – Williamson to Jenifer

24583  Cantwell Ct

 

 

Area 18 (South): 6-8 runs per day

Run ID Run Description

18096  Greenway Cross (Applegate to Beltline Frontage Rd)

18096.2           Fish Hatchery Rd (Greenway Cross – Post Rd)

18096.3           Greenway Cross – Bryant Rd

18097  Stewart St (Applegate to Perry)

18099  Syene Rd (Stewart St – Post Rd)

18100  Watford Way (Stewart St – Post Rd)

18101  Kingsley Way – Watford Way

18103  Watson Ave (Watford Way – Syene Rd)

18104.1           Watson Av – Post Rd

18104.2           16″ Post Rd

18105  Post Rd (Watford Way – Latham Dr)

18107  Union Pacific RR – Whalen Ln

18107.3           W Beltline Frontage Rd – Bike Path to 1702 W Beltline

18108  W Badger Rd – Todd Dr – Service Rd

18108.1           Service Rd West of Todd Dr

18109  Whalen Ln

18110  Damon Rd (W of Whalen Ln)

18111  Service Rd (Coho St – Todd Dr)

18112  Todd Dr (Service Rd – Greenway View)

18113  Mcdivitt Rd – Ashford Ln

18114  Ardsley Ln – Ashford Ln

18115  McDivitt Rd (W of Todd Dr)

18116  Ardsley Cir

 

 

Area 12 (West): 3-5 runs per day

Run ID Run Description

12143  Segoe – Hillview to Tocora

12144  Hillview Ter

12145  Edward Ter – Tokay to Hillview

12146  Hilltop Dr – Tokay to Ames

12147  Segoe – Hillview to Mineral Point

12148  Segoe – Mineral Point to Hilltop

12149  Agnes Dr

12150  Piper Dr

12151  Ames St

12152  Orchard Dr – Mineral Point to Piper Dr

12153  Orchard Dr – Odana to Ames St

12154  Charles Ln – Odana to Ames St

12155  Charles Ln – Keating Ter to Ames St

12156  Woodside Ter – Tokay to Keating Ter

12157  Togstad Glen – Tokay to Keating

12158  Midvale – Tokay to Keating Ter

12159  Keating Ter and Woods End

12160  Mineral Point – Midvale to Parklawn

12161  Mineral Point – Orchard to Parklawn

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.